Thursday, March 16, 2017

Surveying and Leveling

Surveying and Leveling


Definition:
A line joining points of equal elevations is called a contour line. It facilitates depiction of the relief of terrain in a two dimensional plan or map.
Characteristics of contour:
The principal characteristics of contour lines which help in plotting or reading a contour map are as follows:
  1. The variation of vertical distance between any two contour lines is assumed to be uniform.
  2. The horizontal distance between any two contour lines indicates the amount of slope and varies inversely on the amount of slope. Thus, contours are spaced equally for uniform slope
  3. The steepest slope of terrain at any point on a contour is represented along the normal of the contour at that point. They are perpendicular to ridge and valley lines where they cross such lines.
  4. Contours do not pass through permanent structures such as buildings.
  5. Contours of different elevations cannot cross each other (caves and overhanging cliffs are the exceptions). 
  6. Contours of different elevations cannot unite to form one contour (vertical cliff is an exception). 
  7. Contour lines cannot begin or end on the plan.
  8. A contour line must close itself but need not be necessarily within the limits of the map.
  9. A closed contour line on a map represents either depression or hill . A set of ring contours with higher values inside, depicts a hill whereas the lower value inside, depicts a depression (without an outlet).
  10. Contours deflect uphill at valley lines and downhill at ridge lines. Contour lines in U-shape cross a ridge and in V-shape cross a valley at right angles. The concavity in contour lines is towards higher ground in the case of ridge and towards lower ground in the case of valley . 
  11. Contours do not have sharp turnings.
Contour Interval:  
The vertical distance between any two consecutive contours       is known as a contour interval. For example, if the various   consecutive contours are 100m, 98m,96 m etc., then the contour interval is 2m. This interval depends upon,
  • The nature of the ground
  • The scale of the map and
  • The purpose of  survey
Contour intervals for flat country are generally small, eg. 0.25m, 0.5m,  0.75 m etc. For a steep slope in hilly area is greater, eg. 5m, 10m,  15 m etc.
Again ,for a small-scale map, the interval may be of 1m,2m,3m etc. and for large scale map,it may be of 0.25m,0.50m,0.75m etc.
It should be remembered that the contour interval for a particular map is constant. 
Contouring:
The process of locating these contour lines on the surface of the earth is known as contouring.  
Methods of contouring:
The method of establishing / plotting contours in a plan or map is known as contouring. It requires planimetric position of the points and drawing of contours from elevations of the plotted points. Contouring involves providing of vertical control for location of points on the contours and horizontal control for planimetric plotting of points. Thus, contouring depends upon the instruments used (to determine the horizontal as well as vertical position of points). In general, the field methods of contouring may be divided into two classes:
  1. Direct methods
  2. Indirect methods
Direct Method:
In the direct method, the contour to be plotted is actually traced on the ground. Points which happen to fall on a desired contour are only surveyed, plotted and finally joined to obtain the particular contour. This method is slow and tedious and thus used for large scale maps, small contour interval and at high degree of precision. 
Vertical control : 
In this method, a benchmark is required in the project area. The level is set up on any commanding position and back sight is taken on the bench mark. Let the back sight reading on the bench mark be 1.485 m. If the reduced level of the bench mark is 100 m, the height of instrument would be 100 + 1.485 = 101.485 m.
To locate the contour of 100.5 m value, the staff man is directed to occupy the position on the ground where the staff reading is 101.485 -100.500 = 0.985 m. Mark all such positions on the ground where the staff reading would be 0.985 m by inserting pegs. Similarly locate the points where the staff reading would be 101.485 -101 = 0.485 m for 101m contour.
The contour of 101.5 m cannot be set from this setting of the instrument because the height of instrument for this setting of the instrument is only 101.485 m. Therefore, locating contours of higher value, the instrument has to be shifted to some other suitable position.
Establish a forward station on a firm ground and take fore sight on it. This point acts as a point of known elevation, for shifting the position of the instrument to another position, from where the work proceeds in the similar manner till the entire area is contoured.
Horizontal control :
The horizontal control is generally provided by method of plane table surveying or locating the positions of points.
Indirect method of contouring:
In this method, the spot levels of selected guide points are taken with a level and their levels are computed. The horizontal positions of these points are measured or computed and the points are plotted on the plan. The contours are then drawn by a process called interpolation of contours from the levels of the guide points. The following are the indirect methods are commonly used for locating contours.
  1. Squares or Grid method
  2. Cross section method
Square or grid method:
In this method, the area to be surveyed is divided into a grid or series of squares. The grid size may vary from 5 m x 5 m to 25 m x 25 m depending upon the nature of the terrain, the contour interval required and the scale of the map desired. Also, the grids may not be of the same size throughout but may vary depending upon the requirement and field conditions. The grid corners are marked on the ground and spot levels of these comers are determined by leveling. The grid is plotted to the scale of the map and the spot levels of the grid corners are entered. The contours of desired values are then located by interpolation. Special care should be taken to give the spot levels to the salient features of the ground such as hilltops, deepest points of the depressions, and their measurements from respective corners of the grids, for correct depiction of the features. The method is used for large scale mapping and at average precision. 
Cross section method:
In these sections, a base line, centre line or profile line is considered.  Cross sections are taken perpendicular to this line at regular intervals.  After this points are marked along the cross sections at regular intervals.  A temporary bench mark is set up near the site.  Staff readings are taken along the base line and the cross sections. The readings are entered in the level book the base line and the cross sections should also be mentioned.  The RL of each of the points calculated.  Then the base line and cross sections are plotted to a suitable scale.  Subsequently the RLs of the respective points are noted on the map, after which the required contour line is drawn by interpolation
This method is suitable for route survey, when cross sections are taken transverse to the longitudinal section.
Method of interpolation of contours:
The process of locating the contours proportionately between the plotted points is termed interpolation.  Interpolation may be done by:
  1. Arithmetical calculation
  2. The graphical method
By arithmetical calculation
Let A and B be two corners of the squares.  The RL of A is 98.75 m, and that of B 100.75 m.  the horizontal distance between A and B is 10m.
Horizontal distance between A and B = 10m
Vertical difference A and B = 100.75-98.75=2m
Let a contour of 99.00 m be required.  Then,
Difference of level between A and 99.00m contour = 99.00-98.75=0.25m
Therefore, distance of 99.00 m contour line form A= 10/2 *0.25=1.25m
This calculated distance is plotted to the same scale in which the skeleton was plotted to obtain a point of RL of 99.00 m.
Similarly, the other points can be located.
By graphical method
On a sheet of tracing paper, a line AB is drawn and divided into equal parts.  AB is bisected at C and a perpendicular is drawn at this point.  A point O is selected on this perpendicular line and then radial lines are drawn from O to the divisions on AB.  After this lines 1-1, 2-2, 3-3….are drawn parallel to AB.  These lines serve as guide lines.  Boundary line and every fifth the line is marked with a thick or red line.
Suppose we have to interpolate a 2m contour between two points a and b of RLs 92.5 and 100.75m.
Let us consider the lowest radial line OB to represent an RL of 90.00. So, every fifth line will represent 95,100,105, etc.  The tracing paper is moved over the plan until ‘a’ lies at 92.5 and ‘b’ at 100.25. Line ‘ab’ should be parallel to AB.  Now the points 94, 96, 98,100 are picked through to obtain the positions of the required contours.
Method of interpolation of contours:
The process of locating the contours proportionately between the plotted points is termed interpolation.  Interpolation may be done by:
  1. Arithmetical calculation
  2. The graphical method
By arithmetical calculation
Let A and B be two corners of the squares.  The RL of A is 98.75 m, and that of B 100.75 m.  the horizontal distance between A and B is 10m.
Horizontal distance between A and B = 10m
Vertical difference A and B = 100.75-98.75=2m
Let a contour of 99.00 m be required.  Then,
Difference of level between A and 99.00m contour = 99.00-98.75=0.25m
Therefore, distance of 99.00 m contour line form A= 10/2 *0.25=1.25m
This calculated distance is plotted to the same scale in which the skeleton was plotted to obtain a point of RL of 99.00 m.
Similarly, the other points can be located.
By graphical method
On a sheet of tracing paper, a line AB is drawn and divided into equal parts.  AB is bisected at C and a perpendicular is drawn at this point.  A point O is selected on this perpendicular line and then radial lines are drawn from O to the divisions on AB.  After this lines 1-1, 2-2, 3-3….are drawn parallel to AB.  These lines serve as guide lines.  Boundary line and every fifth the line is marked with a thick or red line.
Suppose we have to interpolate a 2m contour between two points a and b of RLs 92.5 and 100.75m.
Let us consider the lowest radial line OB to represent an RL of 90.00. So, every fifth line will represent 95,100,105, etc.  The tracing paper is moved over the plan until ‘a’ lies at 92.5 and ‘b’ at 100.25. Line ‘ab’ should be parallel to AB.  Now the points 94, 96, 98,100 are picked through to obtain the positions of the required contours.

Wednesday, September 03, 2014

Estimation & Quantity Surveying Two Mark With Answers


Estimation & Quantity Surveying Two Mark With Answers


Department: Civil
Semester: 7
University: Anna University
Subject Name: Estimation & Quantity Surveying Two Mark With Answers

Top Ten Tips To Improve System Speed



Top Ten Tips To Improve System Speed






1.Let your PC boot up completely before opening any applications. 
2. Refresh the desktop after closing any application. This will remove any unused files from the RAM. 
3. Do not set very large file size images as your wallpaper. Do not keep a wallpaper at all if your PC is low on RAM (less than 64 MB). 
4. Do not clutter your Desktop with a lot of shortcuts. Each shortcut on the desktop uses up to 500 bytes of RAM. 
5. Empty the recycle bin regularly.The files are not really deleted from your hard drive until you empty the recycle bin. 
6. Delete the temporary internet files regularly. 
7. Defragment your hard drive once every two months. This will free up a lot of space on your hard drive and rearrange the files so that your applications run faster. 
8. Always make two partitions in your hard drive. Install all large Software's (like PSP, Photoshop, 3DS Max etc) in the second partition. Windows uses all the available empty space in C drive as virtual memory when your Computer RAM is full. Keep the C Drive as empty as possible. 
9. When installing new Software's disable the option of having a tray icon. The tray icons use up available RAM, and also slow down the booting of your PC. Also disable the option of starting the application automatically when the PC boots. You can disable these options later on also from the Tools or preferences menu in your application. 
10. Protect your PC from dust. Dust causes the CPU cooling fan to jam and slow down thereby gradually heating your CPU and affecting the processing speed. Use compressed air to blow out any dust from the CPU. Never use vacuum.

Hydrology Two Mark With Answers

Hydrology Two Mark With Answers




Department: Civil
Semester: 7
University: Anna University
Subject Name: Hydrology

 

Saturday, August 30, 2014

Role of a Site Engineer Buildings

    Role of a Site Engineer Buildings


  As a site engineer, in a construction project of high rise buildings, you carry a lot of responsibility to finish the project in time and with cent percent accuracy. As we know, construction projects are generally a one time activity and are irreversible in nature. Hence, it is on site engineer to inspect the activities/work on construction site and ensure that everything is going as per the schedule, plan & design. In this article, we have tried to cover all the aspects of construction project and the points that a site engineer has to keep in his mind during his inspection of the field. In a way, these points reflect the role and responsibilities of a site engineer in a construction project of high rise buildings. 

BRICK WORK 
1.During the brickwork, the vertical alignment of bricks has to be constantly checked, while piling brick, with the help of plumb-bob attached to a rope. 
2.For 9-inch wall, the rod is not necessary. But for brick-work of 4 ½ inch wall, a single rod has to be placed after each 5 layers of brick. 
3.During brick-work, the brick should be wetted in water before using it in brick work of wall. 4.During brickwork there must be kept small gap between bricks and the gap must be filled properly with cement mix prepared. 
5.Chipping must be done in the beams and columns before brick work. 

CASTING OF SLAB, BEAMS AND COLUMNS
 1.The props used for supporting shuttering plies (during casting of slab and beam) must be kept perfectly vertical and the gaping between these props shouldn’t exceed 1m. Props must be properly tightened. 
2.During casting of slab, the concrete mix shouldn’t leak from down-side of shuttering plies. If so, it should be checked and hole must be blocked. 
3.Spacing of rings and formwork should be checked using the drawing of beams and slabs. 4.Leveling of slabs and beams (shuttering plies) has to be checked using theodolite before casting. 5.Small pieces of concrete block have to be inserted below formwork to maintain the spacing. 
6.The plywood used for supporting the slab should be changed after using it for casting slabs 3-4 times. 

FINISHING 
1.90 degree has to be maintained in all nooks and corners of room while plastering or finishing. 
2.Finishing of Plaster work must be checked. 
3.Alignment of walls, ducks should be checked. 
4.Dimensions of windows, doors & other elements of room should be checked.

Set video as desktop wallpaper in computer

Set video as desktop wallpaper in computer



                Ever wanted to set cool videos as your computers Desktop Wallpaper, then you came to right place. Today in this post i will teach you how to set videos as your Desktop Wallpaper with a simple nice little trick and small tool or software that mostly every one has installed on their computer or laptop. This trick works on Windows Xp as well as it works on windows 7. 
Go through below post to learn this simple trick. How to set video as desktop wallpaper ? 
1. Open VLC Media Player. If you don't have it download it frome Here. 
2. Then Go to Tools > Preference Or press CTRL + P and Selecet Video from left panel 
3. Then Choose DirectX video output from output dropdown list as shown in below image . 
4. Save the changes ans restart VLC Media Player. 
5. Play any video you would like to set as your desktop wallpaper. 
6. Then click on Video and select DirectX Wallpaper from the dropdown list as show in below image. 7. Now Minimize vlc player and you will see your video running on your desktop as wallpaper. 
8. If you want your default wallpaper back then uncheck DirectX Wallpaper from video dropdown list. 
9. Hope you like this simple trick.